General Meeting Information

Date: January 28, 2025
Time: 2:00-3:00pm
Location: Via Zoom*

*Contact the Admin. for Zoom information 


  • Agenda

    Time Topic Purpose Discussion Leader
    2:00-2:05 Review/approve notes from October 15, 2024 A DaSilva
    2:05-2:10 Campus Center - First floor refresh update I Lockwood
    2:10-2:20 Campus Center - Second floor refresh update I DaSilva
    2:20-2:25 Resource Hub project update (formerly Food Pantry)  I Lockwood
    2:25-2:35

    Measure G update

    • All gender restrooms 
    • Flint Center
    • Beach Volleyball
    • Creative Arts
    I DaSilva
    2:35-2:40

    Information sharing/Quick news

    I All

    A = Action
    D = Discussion
    I = Information

  • Minutes [DRAFT]

    Campus Facilities

    Meeting Notes

    January 28, 2025


    Review/Approve notes October 15, 2024

    The group reviewed and approved the meeting notes from October 15, 2024.


    Campus Center first floor refresh update

    A project charter has been created, and funding has been identified. A project manager has been assigned, and college operations will collaborate with the district project manager. A question was raised regarding the installation timeline for Zoom capabilities in the Student Council Chambers. Facilities requires a utility person to install the necessary backing for this part of the project. The main electrical work has been completed.


    Campus Center second floor refresh update

    ETS will explore upgrades in the Fireside Dining Room, Don Bautista Room, and Conference Rooms A and B. A complete refresh of the main dining room’s equipment is also planned. The project still needs to go out to bid, and progress is expected later. Aesthetic updates, including painting, will be part of a second phase.


    Resource Hub project update (formerly Food Pantry

    The project charter is complete, funding has been identified, and a project manager has been assigned. A structural architect engineer will be assessing the interior to ensure no additional reinforcements are needed to support new equipment, shelving and supplies. In Fall Quarter 2024, the project manager, Dean of Enrollment Services and the FF&E Coordinator visited San Jose State University’s food pantry which serves as inspiration for the new space.


    Measure G update

                All-Gender Restrooms (S6, S2, L5)

    Plans were submitted to the Department of the State Architect and returned with questions for the district. The architect has responded to the inquiries, and once approved the project will move forward. Temporary restrooms and sinks will be provided during the renovations.

                Flint Center Demolition

    Demolition is progressing and rubble removal is underway. Once cleared, the site will be prepared for the construction of the new Creative Arts building.

                Beach Volleyball

    The project is progressing well, and six sand courts with a scoreboard are expected to be completed by summer. Athletic Director, Hannon encouraged the membership to view the site and shared the department’s collective satisfaction with the construction timeline and progress.

                Creative Arts

    Once the Flint Center demolition is completed and the area is prepared, focus will turn to the construction of the new Creative Arts building.


    Information Sharing/Quick News

    Participants/Attendees­­: DaSilva, Gannon, Hannon, Lee, Lisha, Lockwood, Nogra, Pelusi, Shamarao, Vanhoanhan

    Notes: Gore